North of Pine Island Road, two 10,000-square-foot lots can look the same on paper and still come with very different costs that no listing shows. One could sit in North 2, where the city's water, sewer and irrigation lines are finished and the standard assessment is posted at $18,032 if prepaid. Another could sit in North 1 East, where the standard assessment was $32,288 to prepay and the first annual installment, $3,385 a year on the default 30-year plan, is due on the property tax bill this November. A third could sit in North 3, where the city's most recent estimate ran past $41,000 for some parcels before the City Council stopped the project in October to redesign it.
The Utilities Extension Project, or UEP, is how Cape Coral is bringing city utilities to the last unserved areas north of Pine Island Road. Most of the city south of that road already has them. Because a financed assessment stays with the property when it sells, the phase a lot sits in can matter about as much as its square footage.
At an October council workshop, the city manager explained the assessment math in one line, as reported by the Cape Coral Breeze. The project's cost is divided by the number of equivalent parcels in the area, and the result is the assessment. "You increase the numerator and hold the denominator the same, the quotient grows," he said.
An equivalent parcel is 10,000 square feet, the typical residential lot in Cape Coral. The city's finance director said 93.5% of North 3 parcels fall between one and two equivalent parcels, so oversized lots pay more. The full bill also has two parts. A line-extension charge, based on land area, pays for the mains in the street. A capital facility expansion charge, based on equivalent residential units, pays for treatment and transmission.
Every area has its own costs and its own parcel count, so every area ends up with its own number. Being in the same part of the city doesn't mean paying the same amount.
Here is where the main North Cape areas stood in October 2026, using the city's figures for a standard 10,000-square-foot parcel getting all three services:
| Area | Status | Standard-parcel assessment |
|---|---|---|
| North 2 | Construction complete; work began November 2017 | $18,032 prepaid, $20,726 financed |
| North 1 West | Substantially complete; availability notices sent | $33,367 prepaid, $35,930 financed |
| North 1 East | Under construction; notices to proceed began December 2025, completion targeted for end of 2027 | $32,288 prepaid, $33,142 financed |
| North 3 | Paused for redesign and rebid | Pre-pause estimate of $35,264 east of Burnt Store Road and $41,029 west |
| North 5 and North 6 | Study stage | Not yet set |
| North 7 | Labeled "TBD" on the city map | Not yet set |
North 1 East is the next area to reach the tax bill. Its prepayment windows closed on July 31, 2026, and any balance not paid in full defaults to a 30-year payment plan at a maximum estimated interest rate of 6.25%. The first annual installment is billed in November 2026. For a standard lot, the Cape Coral Breeze reported in November 2025 that annual payments would be $3,385 over 30 years, $3,616 over 25 years or $3,961 over 20 years.
North 2 is the cheapest line in the table because its work started back in 2017. Mayor John Gunter made the same point at a September meeting, according to the Cape Coral Breeze, saying the city is five years behind schedule on utility expansion and that owners would have paid "substantially less" if the work had been done earlier.
North 3 changed course in less than three weeks. At a packed special meeting on September 28, the council voted 5–3 against pausing the project and passed its initial assessment resolutions, according to the Cape Coral Breeze. Gunter argued against waiting:
"If we come back 12 to 18 months from now, no matter who is sitting, the cost is going to be higher than it is today. The data tells us this. Make your decision based on data."
The estimates presented that night were $35,264 per equivalent parcel east of Burnt Store Road and $41,029 west of it. The west-side figure included "Alternative 5," a road rebuild that moves the roadway toward the center, adds a multi-use path and leaves about 20 extra feet at the edge of each driveway. That option added $5,765 per equivalent parcel.
Alternative 5 is where the plan came apart. At a workshop on October 14, the Cape Coral Breeze reported, the council reached consensus to remove Alternative 5, redesign the roadwork and rebid construction. City staff put the difference between Alternative 5 and a standard road restoration at $17,246,603.37 across 6,157.2 equivalent parcels. The homeowner information meeting set for October 19 was canceled, and bidders are being told the contract will not be awarded.
Removing Alternative 5 doesn't bring the west side down to the east-side number. The city still has to rebuild the road. Staff said a standard UEP road restoration costs $2,964 per equivalent parcel, which puts the west-side base at $38,228. The redesign itself costs about $3 million, and Gunter said that amount should not be added to the assessments. Councilmember Keith Long said plainly that "the cost will increase" with a rebid.
The pause becomes official only when the council votes to repeal the three assessment resolutions at its November 2 meeting. That is the day before the general election, with four of the eight council seats on the ballot. After that, the new council decides the redesigned project's scope and cost. North 3 lots therefore carry the least predictable number on the map. Their current estimate is a figure from before the pause, and both the mayor and a council member have said the next one will likely be higher.
This is why the phase matters to a buyer as well as to the current owner. The city's UEP FAQ says an owner paying in installments typically does not have to pay off the balance when selling, because "the assessment continues to be assessed against the property regardless of the owner." There are exceptions, including some public acquisitions and an outstanding tax certificate that the city chooses to accelerate. The FAQ also notes that some lenders may require full payment.
North 1 East's final resolution says the annual assessments are liens on the property with the same rank and priority as tax liens. On the tax bill, the Lee County Tax Collector adds non-ad valorem charges like these to the regular property tax. Anyone can look up a bill by address.
The tax estimates buyers see online won't show these charges. Under Florida Statutes §689.261, the buyer disclosure summary covers ad valorem property taxes. Starting February 1, 2027, listing platforms must show estimated ad valorem taxes along with a disclaimer that the estimates leave out non-ad valorem assessments.
To see what a specific parcel owes, the city's CapeIMS page shows open balances, including UEP assessments. Anyone can also request a free written payoff for any parcel. The timing matters this fall. Annual installments are calculated in August and September, so any payoff figure provided after July 31 is an estimate until billing is finished. The city recommends a written payoff request before a scheduled closing.
The joint Florida Realtors and Florida Bar residential contract handles public-body assessments in paragraph 9(f). The December 2024 version says the seller pays liens "certified, confirmed and ratified before Closing." The seller also pays the public body's latest estimate for an improvement that is "substantially complete as of Effective Date" but hasn't become a lien yet. The clause then says, "Buyer shall pay all other assessments."
For assessments paid in installments, the form gives two choices. Option (a) has the seller pay installments due before closing and the buyer pay those due after, with the closing year prorated. Option (b) has the seller pay off in full any assessment the public body allows to be prepaid. If neither box is checked, option (a) applies. The joint "AS IS" form uses the same language.
A North 3 lot has no final assessment yet, and its assessment resolutions are scheduled for repeal. This is general information, not legal, tax or financial advice. How paragraph 9(f) applies to a particular parcel is a question for your real estate attorney or title company.
The assessment pays for the lines in the street. Connecting the house is a separate cost. According to the city's connection guide, developed properties generally must connect to water and sewer within 180 days after the city's Notice of Availability. Septic tanks can stay in the ground but must be collapsed and abandoned.
So a North 1 East home that is still on septic carries two costs, the annual installment that starts this November and the connection work that follows the availability notice.
Does a finished area like North 2 still show up on a tax bill? It can, if the owner chose installments. The balance is removed only after both the annual installment and the remaining principal are paid.
Can an owner prepay some services and finance others? Yes. The city allows a different payment choice for each of the water, wastewater and irrigation assessments.
Is there help for owners who can't afford the payments? For North 3, the city's finance director described two programs. One is a hardship deferral of annual payments for owners who meet income limits. The other is a Community Development Block Grant program that covers connection, septic abandonment and meter fees for very-low-income families.
If you're comparing lots or homes north of Pine Island Road and want to know which phase each one sits in before you make an offer, Emily Durgan can help you request the city's payoff for each parcel. Let's connect.